Oxford Science Park

Project Overview

 

Location

Oxford

 

Start/End date

March 22 – Ongoing

 

Tonnage

2000T

Location

Oxford

 

Start/End date

March 22 – Ongoing

 

Tonnage

2000T

This project comprises of 2 buildings, both will be fabricated and erected by J & D Pierce (Contracts) Ltd, with the first of the two, the Iversen building, finished erection and handed over.

The second, the Leggett building, to start some time in 2023.

This project was fabricated at both our Glengarnock facility and our facility in East Kilbride ( Strubeam ) then painted in the Glengarnock Main works paint shop. It had tight access due to railway restrictions and minimal building external footprint, another project completed ahead of programme despite its challenges.

The 86,000 sq ft laboratory and office Iversen Building will be completed in the summer of 2023, providing high-specification grow-on space for science and technology companies.

The 78,500 sq ft Leggett Building will be completed the following year.